While many on-site work activities are the same regardless of construction materials, there are some specific differences that should be understood when working with LGS. In this Working on Site series, you will find topics to assist with the preparation and installation of LGS frames on-site, including types of fasteners, bracing, thermal breaks and Dampcourse protection.

This video provides an overview of the key steps from setting out to installing LGS wall frames on site.

Erecting two wall frames

(0:03) As carpenters you'll be familiar with laying your frames in line with your site lay plans. We'll now show you how to stand a wall frame and pre-cut a bottom plate for a door opening.

(0:15) One of the most critical elements when building a light gauge steel home is to follow your steel frame fabricator’s installation guidelines and instructions.

(0:35) These will include specific site lay plans as well as the manufacturer's proprietary system details such as connections and markings. Each steel frame system will have their own format for marking frame components.

(0:51) In this example the Enduro CAD system stamps their markings on the outside face of the components.

(0:59) In this example TAFE_SESSION is the job ID. W003EXT is the frame number; 2-BP is the part usage; 1998 is the part length.

(1:15) The actual process of building with a steel frame is very similar to building with any other material. Correctly marking out the slab to position the frame on site as per the site plan involves the same techniques and skills.

(2:24) Some frame manufacturers will also provide their plans in 3D format that allows you to view the build in more detail and from various angles.

(2:34) To protect the steel framing from ground moisture, an impermeable membrane should be installed under all perimeter bottom plates fixed to concrete slabs on ground. The membrane should extend up the weather side flange of the bottom plate. Membranes may be factory applied or you may need to apply it on site.

(3:26) Following your frame installation instructions, stand the first two walls and temporarily clamp. Here an automatic self-adjusting c-clamp is used.

(4:08) To fix the walls, ensure your fasteners comply with the fabricator's instructions, in terms of mechanical properties, gauge, size and durability. As a minimum, they must have equivalent durability to the frame. The correct choice of fastener is critical to long term performance when fixing steel products. Fasteners used to fix your steel framing must be suitable for corrosivity environment Category 3 or higher. Fastener providers have posters showing types and application. Here is an example of one from Buildex.

(5:45) Prior to erecting the wall it is more efficient to pre-cut just the bottom plate of door openings for ease of later removal.

(6:17) When frames are clean cut, no further corrosion protection is required.

(6:30) Bracing should not be done too early in the build as you may find that some walls will not align. This might be due to an uneven slab. Bracing should always be completed before moving on to trusses for safety reasons. Temporary braces are left in place permanently. To adjust the frame, remove the bottom fastener from the K brace.

(7:20) Adjust the brace until the stud is plumb, then secure with two fasteners on the inside and outside of the plate.

(8:08) Strap bracing is another form of bracing. The frame is plumbed by tightening or loosening the strap tensioners. The straps are then fixed to each frame member they cross. Sheet bracing is another form of bracing that may be used.

(9:02) Tie-down bolts should be installed to the slab edge in accordance with the distance required to meet the uplift performance and following the installation method specified and in accordance with engineering requirements for frame tie-down.

(9:14) A steel frame does not require drilling multiple threaded rods from the base through to the top plates, as wall studs and bracketry can meet the tie-down requirement. Different systems have different tie-down solutions.

(9:29) Here the EnduroCAD system uses a bent tab to connect the stud and frame to the slab. These design solutions make tie-down in the frames easy and quick.